The Town of Evansville hired WLC for various phases of the 2025 sidewalk improvements project. Beginning with grant application assistance, WLC helped the Town of Evansville with grant writing to secure project funding. Our team then performed land surveying services to develop design plans for new sidewalk on portions of 1st, 2nd, 3rd, Texas, Williams, King, Leavitt, and Evans Streets in Evansville.
During the grading design phase of the project, it was critical for our team to individually analyze each property to ensure the new sidewalk and grades would accommodate existing access and drainage to each residential home. Additional services included construction contract administration, construction observation, and materials testing.
Upon completion, residents in Evansville will enjoy new sidewalks along the streets, allowing for safe pedestrian traffic throughout the neighborhood.